Collaboration between concrete pump and concrete batching plant

Concrete pump and concrete batching plant are two core equipments for concrete construction in modern construction projects. The two work closely together in the whole process of concrete production, transportation and pouring, and together constitute an integrated system of "production-transportation-pouring".
Functional positioning: clear division of labor but inseparable
1. Concrete batching plant: "production plant" of concrete
The core function of the concrete batching plant is to produce concrete that meets the requirements according to the designed proportion. It is accurately measured through the batching system (cement, aggregate, water, admixture, etc.), and the finished concrete is output after forced mixing by the mixing main machine. According to the purpose, it can be divided into:
Commodity concrete mixing station: supply to the market, serving multiple construction sites;
Special engineering mixing station: serving a single large-scale project (such as high-speed rail, hydropower station), which needs to be deeply matched with the construction progress.
2.Concrete pump: "transport pipeline" of concrete
The core function of the concrete pump is to efficiently and stably transport the concrete produced by the concrete batching station to the pouring site. It drives the piston or screw through the hydraulic system to push the concrete along the pipeline (or distributing arm) to the designated location. Common types include:
Trailer concrete pump (trailer pump): transported by tractor, flexible to complex sites;
Concrete pump truck: comes with arm (distributing arm), no additional pipe laying is required, suitable for high-rise/narrow space;
Onboard pump: integrated into the chassis, taking into account mobility and pumping capacity, suitable for medium-sized projects.
Essential relationship: The mixing station is the "source" of concrete, and the pump is the "transportation channel". The two together solve the space and efficiency problems of concrete from "production" to "use".
Collaborative process: closed loop from production to pouring
The collaboration between the two runs through the entire concrete construction cycle, and the typical process is as follows:
Demand triggering: According to the construction progress (such as pouring location, volume, time requirements), determine the concrete strength grade (C15-C60), slump (120-230mm), aggregate particle size (usually ≤40mm) and other parameters.
Mix station production: The mix station feeds materials according to the proportion → metering → mixing (usually mixing time is 15-30 seconds) → discharging (through a mixer truck or directly connected to the pump feed port).
Pumping and transportation:
If a trailer pump/truck-mounted pump is used, the mixer truck transports the concrete to the site and unloads it into the pump hopper;
If a pump truck is used, the mix station can directly feed the pump truck hopper through a belt conveyor or a mixer truck.
Casting construction: The pump transports concrete to the formwork, steel cage or working surface through a pipeline (or boom) to complete the casting.
Feedback adjustment: Concrete properties (such as slump loss and workability) need to be monitored during construction. If abnormal (such as pipe blockage), the mix station needs to adjust the proportion (such as increasing the amount of admixture) or the pump needs to adjust the pressure/pumping speed.
Key point: The discharging speed of the mixing station must match the suction/conveying capacity of the pump (for example, if the mixing station produces 60m³ per hour, the pump needs to deliver ≥60m³ per hour), otherwise it will cause pipe blockage (oversupply) or stop work for material (shortage).
Third, technical parameter matching: the core element of mutual restriction
The synergistic efficiency of the two is highly dependent on the matching of technical parameters, mainly involving the following dimensions:
1. The two-way constraints of concrete performance requirements on the two
Aggregate particle size: The maximum aggregate particle size of pumped concrete must be ≤1/3 of the inner diameter of the pump pipe (for example, the inner diameter of the pump pipe is 125mm, and the aggregate is ≤40mm); if the aggregate particle size produced by the mixing station exceeds the standard (such as 50mm), it will cause the pump pipe to be blocked.
Slump and workability: Pumped concrete must have good fluidity (slump is usually 180-220mm), otherwise it is easy to segregate (coarse aggregate sinks and mortar floats), which affects both pumping (pipe blockage risk) and casting quality (uneven structure). The mixing station needs to control the slump by adjusting admixtures (such as water reducers) and water consumption.
Air content: The appropriate amount of air content (2%-4%) can improve the fluidity of concrete, but too high air content will increase the pumping pressure loss, which requires precise control of the mixing station.
2. The reverse effect of pump performance on mixing station design
Delivery pressure and height: High-rise pumping (such as above 300 meters) requires the pump to have high-pressure output (pumping pressure ≥18MPa). At this time, the mixing station needs to produce low-bleeding, high-cohesive concrete (reduce pipe blockage caused by pressure loss).
Delivery flow and speed: The theoretical delivery volume of the pump (such as 150m³/h) determines the minimum capacity of the mixing station (needed to be ≥150m³/h), otherwise it cannot meet the continuous pouring requirements.
Material distribution range: The arm length of the pump truck (such as 56 meters, 63 meters) determines the pouring radius. The mixing station needs to plan the supply route according to the coverage of the pump truck (such as the transportation distance of the mixer truck ≤30 minutes by car).
3. Control system linkage requirements
In modern projects, mixing stations and pumps are often linked through PLC or IoT systems:
The concrete batching station can automatically adjust the production rhythm according to the real-time needs of the pump (such as pumping speed, remaining volume);
The pump blockage alarm can be fed back to the mixing station to trigger the ratio correction (such as increasing the amount of admixture);
The IoT platform can integrate the data of the two (such as production efficiency and energy consumption) to optimize the overall scheduling.
Application scenarios: Collaborative configuration under differentiated needs
Different types of projects have differentiated requirements for the combination of mixing stations and pumps:
1. High-rise buildings/super high-rise buildings
Demand characteristics: large pouring height (200-600 meters), concentrated volume (single pouring of thousands of cubic meters), short time window (mainly night construction)
Coordinated configuration:
Mix station: "Dual machine and dual control" (two sets of mixer main units in parallel) is required to ensure continuous feeding;
Pump: High-arm pump trucks (such as 67 meters, 70 meters) or multiple drag pumps are preferred for relay pumping;
Key points of cooperation: Mix station needs to produce high-grade (C50-C80) and low slump (160-180mm) concrete (reduce high-altitude segregation), pumps need to adjust pumping pressure (stage pressurization) and lubricate pipes regularly (cement slurry lubrication pipelines).
2. Large bridge/cross-sea projects
Demand characteristics: construction sites are scattered (such as offshore platforms, bridge piers), transportation distances are long (mixer trucks need to travel more than 30 kilometers round trip), and the environment is harsh (salt spray corrosion).
Coordinated configuration:
Mixed concrete mixing station: adopt "mobile mixed concrete mixing station" (such as modular design), and arrange it near the bridge pier;
Pump: give priority to vehicle-mounted pump (strong mobility) or trailer pump (adapt to narrow bridge deck);
Key points of coordination: the mixed concrete mixing station needs to add anti-corrosion admixture (resistance to chloride ion corrosion), the pump needs to shorten the pipeline (reduce elbows and reduce resistance), and clean the pipeline regularly (to prevent salt crystallization and blockage).
3. Subway/tunnel engineering
Demand characteristics: small working space (such as shield section), dynamic changes in pouring points (as shield machine advances), and concrete needs to solidify quickly (to prevent deformation of initial support).
Synergistic configuration:
Mixed concrete station: Use "miniaturized mixed concrete station" (30-50m³ per hour) and arrange it close to the face;
Pump: Choose a small displacement drag pump (such as 30m³/h) or a concrete delivery pipe (φ100mm thin pipe) to adapt to narrow spaces;
Key points of coordination: The mixed concrete station needs to produce early-strength concrete (add early-strength agent), the pump needs to reduce the delivery speed (reduce impact wear), and monitor the pump pipe temperature in real time (to prevent the concrete from setting quickly and blocking the pipe).
Economic efficiency and maintenance: Synergistic optimization to reduce costs
The synergistic efficiency of the two directly affects the project cost, and needs to be optimized from three aspects: investment, operation, and maintenance:
1. Investment cost
Separate configuration: Small projects (such as civil construction) can rent mixed concrete stations + pump trucks (total cost of about 500,000 to 1 million yuan);
Overall configuration: Large projects (such as high-speed rail) need to build their own mixed concrete stations + equip multiple pumps (total investment of several million yuan), but the cost can be diluted through scale.
2. Operation cost
Energy consumption: Mixing station (accounting for 30%) and pump (accounting for 40%) are the main energy-consuming equipment, and energy consumption needs to be reduced through frequency conversion control (such as frequency conversion of mixing main motor) and efficient pumping (reducing the number of pipe blockages);
Material loss: Mixing station needs accurate metering (error ≤1%), and pump needs to avoid pipe blockage (a pipe blockage will cause a loss of about 5,000-10,000 yuan per time). The two can work together to reduce concrete waste.
3. Maintenance management
Mixing station: focus on maintaining the mixing main (wear-resistant lining replacement), batching system (sensor calibration), and screw conveyor (lubrication);
Pump: focus on maintaining the pumping system (piston/glass plate wear), hydraulic system (oil filtration), and conveying pipe (inner wall grinding);
Collaborative maintenance: establish equipment ledgers, conduct regular joint inspections (such as synchronously checking the pump pipeline when the mixing station is shut down) to avoid idleness of one party due to failure of the other party.
Sixth, Summary: Integrated coordination is the key to efficient construction
The relationship between concrete pumps and mixing stations is essentially the front-end and back-end coordination of the "concrete production chain": the mixing station determines the "innate quality" (proportion, performance) of concrete, and the pump determines the "acquired fate" (transportation efficiency, pouring effect) of concrete. The matching of the two directly affects the quality of the project, construction progress and cost.
In actual projects, it is necessary to select the type of equipment (such as commodity station/engineering station for mixing stations, pump truck/trailer pump) according to project requirements (volume, height, environment), and achieve integrated operation through parameter matching (aggregate particle size, slump, delivery pressure), system linkage (control system docking), and collaborative maintenance (joint inspection), and finally achieve the construction goal of "efficiency, quality and economy".
- Art
- Causes
- Crafts
- Dance
- Drinks
- Film
- Fitness
- Food
- Games
- Gardening
- Health
- Home
- Literature
- Music
- Networking
- Other
- Party
- Religion
- Shopping
- Sports
- Theater
- Wellness